Vicinity map of Cobblestone Plaza, likely location of Pembroke Pines Supercharger Station with 16 Charging Terminals
Please scroll down to the bottom of this article for current status.
A member of the Tesla Motors Club forum recently discovered a permit for a "Tesla Charging Station" submitted on March 22, 2018 to the City of Pembroke Pines. The address of the location is 14916 Pines Blvd, Pembroke Pines which corresponds to a Chase Bank in the Cobblestone Plaza Shopping Mall.
On this site plan the Chase Bank is located in the center of the property. Also located on the property is a Whole Foods grocery store. Tesla seems to have an arrangement with Whole Foods in that lately Supercharger Stations are frequently sited near their grocery stores. [For a full-sized image, right click and open in a new tab.]
The Tesla website's Find Us map lists a Pembroke Pines "Coming Soon" Supercharger Station targeted for the end of this year. The vicinity map above of the Cobblestone Plaza shows that it is strategically located right off of I-75.
Although the permit information doesn't explicitly use the words Supercharger Station, the language virtually confirms that this is a Supercharger Station with a mention of transformers, control panels, multiple charging stations, fault current, service equipment and control cabinets. It also mentions 16 "charging posts". As a result we are very confident that this is the "Coming Soon" Supercharger Station.
Apparently the permitting folks need more information from Tesla's Electrical Contractor and have denied the electrical application until it is forthcoming.
Update as of May 31, 2018.
Tesla's civil engineering plans were approved on May 31, 2018.
Update as of June 29, 2018.
It looks like the building permits were approved and initial work started in the parking lot. The photo below was provided by a member of the Tesla Motors Club forum.
It appears the Superchargers will be located along the North edge of the parking lot parallel to Pines Blvd between Chase Bank and Whole Foods.
The rectangle in the Google Street View below shows the location of the construction area for the Superchargers.
Update as of October 11, 2018.
The Pembroke Pines Supercharger Station is now operational with 16 - 120 kW charging terminals.